Architect as project manager of Оriginal projects KONNOVA Margarita |
![]() |
"The first start-up complex was built in 2011 .Get on with construction of the 2-nd start-up complex was decided in 2015. The 2-nd start-up complex provided for construction of additional spaces with 2 floors, expansion of existing warehouse – unloading area with 5 overload systems, co-packing area on the first floor, administration and accommodation rooms and office rooms. Additional areas are 2 329,45 m2, technologic communication between floors was made through cargolift, which moves product on pallets with safety. Our company realized field supervision under terms of the contract, support of construction and installation works, consulting, design development and their adaptation to up to date requirements. For example, mercury vapor lamps of industrial luminaires were changed to modern energy saving diode lamps. Realization of the 2-nd start up complex finished expressive elements of architecture of plantbuilding line at prospect Stroiteley".